The Joint River Commission's (JRC) project
for protecting riverbanks on the Sylhet-Assam border and saving the
country's territory from depletion has remained mostly incomplete
although its three-year schedule ended on 30 June this year.
Only Tk 7.6 crore was given in three years against the total sanction of Tk 21 crore for the project.
"The
project is extremely important for saving the country's border as a
26-kilometre stretch along the midstream of Surma and 30 kilometres on
Kushiyara is officially considered the border line with India.
Continuous erosion on the Bangladesh sides of the rivers is causing
depletion of our territory," said Shailen Chandra Paul, executive
engineer of Water Development Board (WDB) in Sylhet.
During the
last 20 years Bangladesh has lost at least 150 acres of land at Amolshid
point, where the Indian Barak River, bifurcating as Surma and Kushiara,
enters Bangladesh.
With recurrent erosion on Amolshid point of
the rivers due to strong current during monsoon, new patches of landmass
has appeared on the Indian side where Indian Border Security Force has
constructed observation towers.
“If measures are not taken,
erosion on other points like Haidrabond, Sharifganj, Bhuiyarmura and
Bhoktipur would take serious turn just with the start of receding water
when erosion is usually triggered by strong current,” said the WDB
official.
Although the three-year project was officially launched
in 2009-2010, it took the authorities a year to hand over the first
installment of Tk 2.75 crore. It was followed by another installment of
only Tk 4.85 crore in 2011-2012, officials informed.
Now two-year
extension is being considered for completing the works, said Abdul
Kalam Azad, superintending engineer, WDB, Sylhet, told this
correspondent.
Late funding along with the contractors' lack of
interest due to remote location of the project work and uncertainty in
payment caused delay in the work, officials said, adding that the delay
will surely lead to cost escalation and further loss of our territory,
said an official.
WDB Executive Engineer of Sylhet Shailen
Chandra Paul said, "Works were hampered mainly due to poor response from
contractors. As for example, tender was called recently for the third
time for Tk 4 crore JRC's protection work at Haidrabond on Kushiyara
riverbank.
The works will be taken up when the ongoing monsoon is over, he said.
In
two years, WDB did some work to partially build the Kushiara dyke but
it is only 3.5 and a half kilometres long against the targeted 12 km.
Due to delay in implementation of the project, erosion took its toll at
places reducing the country's territory on the border areas, sources
said.
But on the other side of the border, the Water Resources Division in Assam has already completed necessary protection works.
The
whole programme was earlier finalised at a joint meeting of officials
of the WDB, Sylhet region, and the officials of the Water Resources
Division of Karimganj, Assam. Besides, the year-wise work plan was
exchanged at an additional chief engineer-level meeting at WDB Rest
House at Zakiganj borders in October 2010.